The Result
PSA BDP provided robust support to execute the operation, even amidst socio-political crises. The team effectively navigated challenges to secure and position the aircraft within the project’s specified timeframe. Additionally, PSA BDP engaged in meticulous planning with EPM’s logistics team to ensure strict adherence to the execution schedule. This effort ensured the project’s successful completion within the established deadlines.
PSA BDP’s support, planning, strategic analysis, solution proposals, 24/7 availability, and experience in handling high-impact projects were instrumental in the project’s success, which in turn, will have major national impact. Hidroituango has an installed capacity of 2,400 megawatts with its 8 generation turbines operating, a sufficient amount of energy to supply 17% of the energy that Colombia demands.
The transportation of these two bulkheads represented a critical milestone for the commissioning of turbines 3 and 4, and therefore the initiation of the country’s most important hydroelectric project. PSA BDP contributed to this through their professional, efficient, and resilient work in overcoming the obstacles that arose over months to meet the schedule.